Milestone
The drainage improvement works have been substantially completed
April, 2018
The construction of 400m (approx.) long box culvert (red section) and river deepening works (light blue section) have been substantially completed. The drainage capacities at the bottlenecks (i.e. junctions at Shatin Pass Road and Tai Shing Street) have been increased by more than 100%. Flood risk to nearby areas is thus significantly reduced.Progress by Year
2018
![]() |
11 June 2018 |
Rehabilitation works adjacent to Wong Tai Sin Police Station are in progress |
More Details |
![]() |
29 March 2018 |
Box culvert construction works from Wong Tai Sin Police Station to Morse Park No. 1 are substantially completed |
More Details |
![]() |
27 February 2018 |
Remaining box culvert construction works next to Kai Tak Garden and Lower Wong Tai Sin Estate commenced |
More Details |
![]() |
31 January 2018 |
River works adjacent to Morse Park No. 1, Kai Tak Garden and Lower Wong Tai Sin Estate are substantially completed |
More Details |
2017
![]() |
01 December 2017 |
River beautification near Tung Tau Estate (II) is in progress |
More Details |
![]() |
28 November 2017 |
Nullah deepening near Lower Wong Tai Sin Estate has completed |
More Details |
![]() |
19 September 2017 |
Nullah deepening near Tung Tau Estate (II) has completed |
More Details |
![]() |
30 June 2017 |
Reconstruction of Jogging Track in Morse Park (Park No.1) has completed and has been opened to the Public |
More Details |
![]() |
29 June 2017 |
Mini-piling works near Wong Tai Sin Police Station and Kowloon Walled-City Community Hall has commenced |
More Details |
![]() |
28 June 2017 |
Construction of Box Culvert near Morse Park No. 1 has completed |
More Details |
![]() |
25 June 2017 |
Construction of Box Culvert near Wong Tai Sin Police Station and Shatin Pass Road has commenced |
More Details |
![]() |
11 June 2017 |
Temporary Traffic Arrangement near Choi Hung Road/ Shatin Pass Road junction has cancelled |
More Details |
![]() |
06 June 2017 |
Construction of Access Ramp near Wong Chung Ming Secondary School has completed |
More Details |
![]() |
27 May 2017 |
Nullah deepening and Construction of Skin Wall near Lower Wong Tai Sin Estate and Kai Tak Garden are in progress |
More Details |
![]() |
28 April 2017 |
Construction of Box Culvert near Wong Tai Sin Police Station has completed |
More Details |
![]() |
28 April 2017 |
Construction of new nullah bed near Tung Tau Estate (II) has completed |
More Details |
![]() |
08 April 2017 |
Mini-piling works near Tung Tai Lane Footbridge has commenced |
More Details |
![]() |
02 April 2017 |
Riverbed and Nullah Wall Construction near Tung Wui Estate has completed |
More Details |
![]() |
30 March 2017 |
Nullah deepening near Tung Tau Estate (II) are in progress |
More Details |
![]() |
27 February 2017 |
Construction of Box Culvert near Kai Tak Garden has commenced |
More Details |
![]() |
03 January 2017 |
Construction of Box Culvert near Kei Tak Primary School has commenced |
More Details |
2016
![]() |
31 December 2016 |
Nullah deepening works and Construction of Skin Wall near Morse Park (No. 1) are in progress |
More Details |
![]() |
30 November 2016 |
Construction of Box Culvert near Morse Park No. 1 has commenced |
More Details |
![]() |
28 November 2016 |
Construction of Pipe Pile Wall near Kai Tak Garden has commenced |
More Details |
![]() |
02 November 2016 |
Riverbed and Nullah Wall Construction near Tung Wui Estate has commenced |
More Details |
![]() |
01 November 2016 |
Riverbed and Nullah Wall Construction near Lower Wong Tai Sin Estate and Kai Tak Garden has commenced |
More Details |
![]() |
31 October 2016 |
Construction of Access Ramp near Wong Chung Ming Secondary School has commenced |
More Details |
![]() |
31 October 2016 |
Construction of Box Culvert near Wong Tai Sin Police Station has commenced |
More Details |
![]() |
28 October 2016 |
Riverbed and Nullah Wall Construction near Wong Chung Ming Secondary School has completed |
More Details |
![]() |
24 October 2016 |
Construction of new Tung Tai Lane footbridge (partial opening to public) |
More Details |
![]() |
29 May 2016 |
Temporary Traffic Arrangement- Choi Hung Road/ Shatin Pass Road junction |
More Details |
![]() |
03 May 2016 |
Morse Park (Park No. 1) Improvement Works has commenced |
More Details |
![]() |
01 April 2016 |
Operate the completed box culvert sections (approximately 200m long) between Shatin Pass Road and Tai Shing Street |
More Details |
![]() |
31 March 2016 |
Riverbed Construction near Ng Wah Catholic Secondary School has completed |
More Details |
![]() |
31 March 2016 |
Riverbed Construction near Wong Chung Ming Secondary School has commenced |
More Details |
![]() |
31 March 2016 |
Riverbed Construction near Choi Hung Road has completed |
More Details |
![]() |
17 March 2016 |
Construction of Box Culvert near Lower Wong Tai Sin Estate has completed |
More Details |
![]() |
20 February 2016 |
Pipe pile Installation near Tung Wui Estate has completed |
More Details |
![]() |
06 February 2016 |
Construction of Box Culvert near Kei Tak Primary School has commenced |
More Details |
![]() |
02 February 2016 |
Riverbed construction near Choi Hung Road has commenced |
More Details |
![]() |
31 January 2016 |
Pipe Pile Installation near Tung Wui Estate has commenced |
More Details |
2015
![]() |
31 December 2015 |
Pipe Pile Installation near Ng Wah Catholic Secondary School has completed |
More Details |
![]() |
31 December 2015 |
Riverbed Construction near Ng Wah Catholic Secondary School has commenced |
More Details |
![]() |
21 December 2015 |
Construction of Box Culvert near Kai Tak Garden has completed |
More Details |
![]() |
14 December 2015 |
Pipe Pile Installation near Lower Wong Tai Sin Estate/Kai Tak Garden has completed |
More Details |
![]() |
26 October 2015 |
Nullah Wall Construction near Ng Wah Catholic Secondary School has completed |
More Details |
![]() |
14 October 2015 |
Nullah Wall Construction near Choi Hung Road has completed |
More Details |
![]() |
14 September 2015 |
Nullah Wall Construction near Tung Tau Estate has completed |
More Details |
![]() |
05 August 2015 |
Nullah Wall Construction near Nga Tsin Wai Village has completed |
More Details |
![]() |
16 July 2015 |
Pipe Pile Installation near Tung Tau II Estate (eastern side of the river) has completed |
More Details |
![]() |
30 June 2015 |
Riverbed Construction near Tung Tau Estate has completed |
More Details |
![]() |
30 May 2015 |
Riverbed Construction near Tung Tau Estate has commenced |
More Details |
![]() |
31 March 2015 |
Riverbed Construction near Nga Tsin Wai Village has completed |
More Details |
![]() |
28 March 2015 |
Pipe Pile Installation near Tung Tau II Estate (western side of the river) has completed |
More Details |
![]() |
26 February 2015 |
Pipe Pile Installation near Tung Tau Estate has completed |
More Details |
![]() |
26 February 2015 |
Pipe Pile Installation near Ng Wah Catholic Secondary School has commenced |
More Details |
![]() |
09 February 2015 |
Riverbed Construction near Nga Tsin Wai Village has commenced |
More Details |
2014
![]() |
31 December 2014 |
Pipe Pile Installation near Wong Chung Ming Secondary School has completed |
More Details |
![]() |
27 December 2014 |
Pipe Pile Installation near Tung Tau Estate has commenced |
More Details |
![]() |
10 December 2014 |
Nullah Wall Construction near Ng Wah Catholic Secondary School has commenced |
More Details |
![]() |
30 October 2014 |
Pipe Pile Installation near Wong Chung Ming Secondary School has commenced |
More Details |
![]() |
30 October 2014 |
Pipe Pile Installation near Kowloon Walled City Community Hall (eastern side of the river) has completed |
More Details |
![]() |
24 October 2014 |
Pipe Pile Installation near Tung Tau II Estate (eastern side of the river) has commenced |
More Details |
![]() |
30 September 2014 |
Pipe Pile Installation near Choi Hung Road has completed |
More Details |
![]() |
23 September 2014 |
Pipe Pile Installation near Nga Tsin Wai Village has completed |
More Details |
![]() |
21 August 2014 |
Nullah Wall Construction near Tung Tau Estate has commenced |
More Details |
![]() |
07 August 2014 |
Pipe Pile Installation near Kowloon Walled City Community Hall (western side of the river) has completed |
More Details |
![]() |
31 July 2014 |
Nullah Wall Construction near Wong Chung Ming Secondary School has commenced |
More Details |
![]() |
31 July 2014 |
Pipe Pile Installation near Choi Hung Road has commenced |
More Details |
![]() |
30 June 2014 |
Pipe Pile Installation near Nga Tsin Wai Village has commenced |
More Details |
![]() |
30 June 2014 |
Pipe Pile Installation near Kowloon Walled City Community Hall (eastern side of the river) has commenced |
More Details |
![]() |
27 June 2014 |
Foundation works for new Tung Tai Lane footbridge has commenced |
More Details |
![]() |
29 April 2014 |
Nullah Wall Construction near Choi Hung Road has commenced |
More Details |
![]() |
29 April 2014 |
Shifting of Choi Hung Road near Tai Shing Street/Tseuk Luk Street/Tung Kwong Road Section has completed |
More Details |
![]() |
12 April 2014 |
Nullah Wall Construction near Nga Tsin Wai Village has commenced |
More Details |
2013
![]() |
30 December 2013 |
Commencement of Midstream Contract No. DC/2013/03 |
More Details |
![]() |
12 December 2013 |
Pipe Pile Installation near Kowloon Walled City Community Hall (western side of the river) has commenced |
More Details |
![]() |
04 September 2013 |
Pipe Pile Installation near Kei Tak Primary School has completed |
More Details |
![]() |
19 March 2013 |
Construction of Box Culvert near Lower Wong Tai Sin Estate has commenced |
More Details |
2012
![]() |
15 December 2012 |
Pipe Pile Installation near Lower Wong Tai Sin Estate/ Kai Tak Garden has commenced |
More Details |
![]() |
31 August 2012 |
Pipe Pile Installation near Kei Tak Primary School (western side of the river) has commenced |
More Details |
![]() |
13 June 2012 |
Pipe Pile Installation near Tung Tau (II) Estate (western side of the river) has commenced |
More Details |
![]() |
23 March 2012 |
Pipe Pile installation near Morse Park (Park No. 1) has commenced |
More Details |
![]() |
01 February 2012 |
Shifting of Choi Hung Road Shatin Pass Road/Tai Shing Street Section has completed |
More Details |
2011
![]() |
01 November 2011 |
Commencement of Upstream Contract No. DC/2011/04 |
More Details |